Rotary Racer 9 - Planner

Rotary Racer 9

Start: June 18, 2012
Finish: November 5, 2012
Report Date: June 17, 2012

Gantt Chart

Week 25, 2012 Week 26, 2012 Week 27, 2012 Week 28, 2012 Week 29, 2012 Week 30, 2012 Week 31, 2012 Week 32, 2012 Week 33, 2012 Week 34, 2012 Week 35, 2012 Week 36, 2012 Week 37, 2012 Week 38, 2012 Week 39, 2012 Week 40, 2012 Week 41, 2012 Week 42, 2012 Week 43, 2012 Week 44, 2012 Week 45, 2012
18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12

Tasks

WBS Name Start Finish Work Complete Cost Assigned to
1 Goals Jun 18 Jun 18 1d 0%
2 Car Design and build Jun 18 Nov 5 37d
2.1 Body shape Jun 18 Jun 18 1d 0%
2.2 Tube design Jun 25 Jun 25 1d 0%
2.3 Build chassis Jul 2 Jul 16 3d 0%
2.4 Rear subframe/Rollbar design Jun 18 Jun 18 1d 0%
2.5 Rear subframe/Rollbar build Jun 25 Jul 9 3d 0%
2.6 Rear subframe/Rollbar fit Jul 23 Jul 30 2d 0%
2.7 Motor fit Aug 6 Aug 20 3d 0%
2.8 Chain drive fitting Aug 27 Sep 3 2d 0%
2.9 Steering Design Jun 18 Jun 18 1d 0%
2.10 Steering Build Jun 25 Jul 16 4d 0%
2.11 Steering fit Jul 23 Aug 6 3d 0%
2.12 Chassis Fit together Sep 10 Sep 24 3d 0%
2.13 Top and Bottom attach Oct 1 Oct 8 2d 0%
2.14 Seat make Jun 18 Jun 18 1d 0%
2.15 Seat fit Oct 1 Oct 1 1d 0%
2.16 Battery mounting and boxes Oct 1 Oct 8 2d 0%
2.17 Sides and behind head Oct 15 Nov 5 4d 0%
3 Electronics Jun 18 Oct 8 3d
3.1 Electronics Design Jun 18 Jun 18 1d 0%
3.2 Electronics Install Oct 1 Oct 8 2d 0%

Resources

Name Short name Type Group Email Cost